Monolith Housing Solution

|

Vancouver Fourplex Net Zero and VBBL Compliance

Net Zero Design and VBBL Compliance: Vancouver Fourplex

For a small multi-unit project in Vancouver, energy compliance is not a single submission. It runs from the first energy model through permit and construction, and ends only when the finished building is tested and documented. Monolith Housing Solutions provided Net Zero energy design and compliance consulting for a new fourplex designed to the Vancouver Building By-law and the Zero Emission Buildings Bulletin.

Project Snapshot

Project: Vancouver Fourplex

Location: Vancouver, British Columbia

Building: New four-unit residential development

Framework: Vancouver Building By-law, City of Vancouver Zero Emission Buildings Bulletin

Service: Energy modelling, design optimization, compliance documents, airtightness testing, EnerGuide and Net Zero support

Software: HOT2000

3D rendering of the Vancouver fourplex designed for Net Zero and VBBL compliance

Why early

Why Vancouver Multiplexes Need Compliance From Day One

In Vancouver, energy and emissions requirements sit in the City's own building by-law, separate from the BC Building Code used by neighbouring municipalities. Assemblies, windows and the heating and hot-water systems are chosen at design stage, so an energy advisor brought in then can test those choices in the model before they are locked into permit drawings.

Stage by stage

The Compliance Process

Stage

Monolith's scope

Design

HOT2000 modelling and optimization; envelope, glazing and airtightness review; heating, cooling, ventilation and hot-water assessment

Permit

Energy compliance documents, Pre-Construction Compliance Checklist, Homeowner Information Sheets

Construction

Airtightness planning and a mid-construction blower door test

Completion

Final site verification and airtightness test, final energy-model update

Close-out

Compliance reporting, EnerGuide and Net Zero documentation support

Energy model

Design Optimization in the Model

1

Envelope Assemblies

Walls, roofs and floors tuned for heat loss.

2

Glazing

Window performance balanced against the rest of the envelope.

3

Airtightness Targets

A target the site team can plan for and test against.

4

Mechanical Systems

Heating, cooling, ventilation and hot water sized for the envelope.

North and west elevation drawings of the Vancouver fourplex

Testing Airtightness Before the Walls Close

Monolith planned airtightness with the project team and ran a mid-construction blower door test while the air barrier was still accessible, so leaks could be fixed without opening finished walls. A final verification test followed at completion.

Closing the Loop With an As-Built Model

At completion, the model was updated to the building as built, including measured airtightness, and the final compliance report prepared with EnerGuide and Net Zero documentation support.

3D rendering of the Vancouver fourplex designed for Net Zero and VBBL compliance

What This Means for a Multiplex Developer

  1. Design decisions tested early.
  2. Permit documents in the form the City expects.
  3. Leakage caught mid-construction.
  4. Final documents that match the building as built.

Planning a Multiplex in Vancouver?

Designing a fourplex, sixplex or other multi-unit home in Vancouver? Monolith Housing Solutions can start with the energy model and stay with the project through final testing.

(604) 723-1364

2030 Marine Dr, North Vancouver, BC

Contact Us

Project Media

Vancouver Fourplex

Design rendering and elevation drawings for the fourplex.

3D rendering of the Vancouver fourplex designed for Net Zero and VBBL compliance North and west elevation drawings of the Vancouver fourplex